Project Description
Client: Qatargas Operating Company Limited.
Location: Ras Laffan, Qatar
Year Completed: Feb-2011
Value: QAR 298 Million
Engineering Consultant: Worley Parson (Overall Engineering)
Role & Scope of Work: Prime EPIC Contractor;
Detailed engineering, materials procurement (Civil, Mechanical, Piping, Equipment, Electrical, Instrumentation, Telecommunication, Blasting, painting, etc.), transport, fabrication, erection, installation of materials and construction, testing and commissioning. Electrical, Instrumentation & Telecom works subcontracted to Cegelec.
The Challenges
Scheduling and execution of the construction and commissioning works inside a busy Jetty, subject to the ship loading window at different jetties.