Project Description
Client: Qatar Energy
Location: Offshore, Qatar
Year Completed: January 2021
Role & Scope of Work:
Prime EPIC Contractor.
The scope of works includes but not limited to Detailed Engineering, Procurement, Installation, Fabrication and T&I, Pre-commissioning, Commissioning, testing and handover of a New WHJ U08C with temporary drilling deck for the new WHP (ISND-U08C) installed in IDD El Shargi North Dome (ISND) field – Four (4) legged jacket, Piles, Temporary drilling deck TDD, Three (3) Pre-installed risers including riser clamps and 5D bends, One (1) Pre-installed J-tube, Two (2) Access ladders and landings from Jacket walkway to TDD, Anodes, Two (2) Levels boat landing, etc.